Your project

Most floor tile is ⅜ in (8–10 mm). Grout fills the joints this deep.

1/16 in for rectified tile, ⅛ in for most floor tile, ¼ in for rustic tile.

Printed on the box or product page.

%

10% for a straight lay; 15% for diagonal, 20% for herringbone.

Bigger tile needs a deeper notch. Lift a tile now and then: mortar should cover at least 80% of its back.

Each gets a transition strip where the floor changes.

Your local prices (optional)
$

Typical US prices; change them to match your store.

$
$
$
$
$
$
$
$
$
Project sheet · Tile Floordiycalcs.org
Plan view (to scale)12'10'12 in × 12 in tile · ⅛ in joints · edge tiles 11⅛ in at the ends, 11¼ in at the sidesSection at the wall (not to scale)Baseboard over the gap; caulk, don’t groutTile ⅜ in, grout joints ⅛ inThin-set, ¼ × ⅜ in square notchCement board, screwed every 8 inThin-set bed, ¼ × ¼ in notchPlywood or OSB subfloor¼ in movement gap at every wallWhole tilesCut tilesStart linesTransition strip × 1Floor 120 sq ft
Shopping list
BoughtItemBuyCost
Floor tile130 tiles with 10% extra, 15 per box; 135 sq ft bought9 boxes$405.00
Thin-set mortar, 50 lb60 sq ft per bag with a ¼ × ⅜ in square notch trowel, plus 85 sq ft per bag under the cement board (¼ × ¼ in notch); polymer-modified for most porcelain4 bags$100.00
Sanded grout, 25 lb9.5 lb for ⅛ in joints ⅜ in deep, with 10% extra; sanded for joints ⅛ in and wider1 bag$25.00
Cement board, ¼ in, 3 × 5 ft120 sq ft + 10% for cuts, 15 sq ft per sheet; seams staggered, never lined up with the plywood seams9 sheets$135.00
Backer board screws, 1¼ inAbout 432 screws: every 8 in across each sheet, jars of 2003 jars$45.00
Alkali-resistant mesh tape, 2 inAbout 42 ft of board seams, 50 ft rolls; embedded in thin-set1 roll$8.00
Tile spacers, ⅛ inAbout one per tile, bags of 2501 bag$6.00
Penetrating grout sealer, 1 quart bottleBrushed on the joints once the grout has cured, a quart per 200 sq ft; check the label1 bottle$20.00
Transition strips, 6 ft1 per 3 ft doorway; a reducer if the tile ends higher than the next floor1$25.00
Estimated materials total$769.00
Tile is rounded up to whole boxes; buy one more if your boxes have different lot numbers. Excludes tax and tools.
Floor area120 sq ft11.15 m²
Tiles to buy135130 needed with 10% extra, rounded up to full boxes.
Edge tiles at the end walls11.06 in28.1 cmLaid out from a grout joint on the center line. Both ends match; measured to a ¼ in gap at the wall.
Edge tiles at the side walls11.19 in28.42 cmLaid out from a grout joint on the center line. Both sides match, so no sliver at one wall.
Grout needed9.45 lb4.29 kgIncluding 10% extra.
Floor rises by about0.94 in2.38 cmTile + mortar bed + cement board on its own bed. Check door clearance and the step to the next floor.

Order of work

  1. Safety first. Old sheet vinyl, vinyl tile and their adhesive in houses built before the 1980s can contain asbestos: have them tested before you scrape or break them up. Cutting tile and cement board makes silica dust, so cut outdoors or wet and wear an N95 mask, safety glasses and hearing protection. Tiling a floor rarely needs a permit, but a bathroom remodel with plumbing work usually does; check with your building department.
  2. Check the floor. Tile needs a stiff, flat floor: most tile makers ask for no more than ⅛ in of variation over 10 ft (1/16 in over 2 ft for tile 15 in and larger). If the floor bounces, have the framing checked before tiling. Grind high spots and fill low ones with a patching compound.
  3. Lay the cement board on a wood subfloor: spread thin-set with a ¼ × ¼ in notch, set the sheets with their seams staggered and off the plywood seams, leave ⅛ in between sheets and ¼ in at the walls, and screw every 8 in. Fill the seams with thin-set and embed the mesh tape.
  4. Snap the start lines. Mark the center of the room both ways, dry-lay a row of tiles with spacers along each line, and shift by half a tile if the planner says so. The cut tiles at opposite walls should match.
  5. Set the tile one quadrant at a time, working toward the door. Comb the mortar in straight lines, back-butter large tiles, and lift a tile now and then to check the coverage. Keep the joints clean and let the mortar cure as the bag says, often 24 hours.
  6. Grout and seal. Pull the spacers, pack the grout in diagonally with a rubber float, and sponge off the haze. After the grout has cured (often 48–72 hours), brush on the sealer. Caulk, don’t grout, the gap at the walls and fit the transition strips and baseboard.

Tools you’ll need

  • Tape measure, chalk line, carpenter’s square and a 4 ft level
  • Notched trowels (sizes on the list), a margin trowel and a mixing paddle on a ½ in drill
  • Manual tile cutter or wet saw, and a tile nipper or angle grinder with a diamond blade for notches
  • Utility knife and straightedge for scoring cement board, and a drill/driver for the screws
  • Rubber grout float, sponges and two buckets
  • Knee pads, safety glasses, gloves, hearing protection and an N95 mask

Tips before you buy

  • Mix tiles from several boxes as you go, and check that every box carries the same shade and lot number before you open any.
  • Rectangular tile 18 in and longer can bow in the middle. Offset the rows by no more than a third of the tile length to keep the edges flush.
  • Large tile needs a flatter floor and a leveling clip system; budget for the clips if your tile is 15 in or longer.
  • Use a grout color close to the tile for a calm floor, or a contrasting one to show off the pattern. Grout cleanup is easier with sealed or glazed tile.