Project planner

Concrete Slab Planner

Enter the size of your patio or pad to get the forms, base, reinforcement and concrete — bags or a truck, whichever is cheaper — priced, with control joints and the order of work.

Your project

4 in for patios, walkways and shed floors; 5–6 in where a car will park. Follow your local code for anything that carries a building.

4 in of compacted gravel is typical; 6 in on clay or wet ground.

Neither stops cracks — control joints do — but both hold cracks tight and level.

Your local prices (optional)
$

For the bag size chosen above.

$

Delivered prices mostly run $150–195 per cu yd.

$

Most suppliers charge a fee below a minimum order, often 3–5 cu yd. Enter 0 if yours doesn’t.

$
$
$
$
$

The board’s price divided by its length.

$
$
$
Project sheet · Concrete Slabdiycalcs.org
Plan view (to scale)House wall12'12'House wallSlopes 3 in →Slab 4 inMesh on chairsGravel 4 inDig 8 in12'Cross-sectionSection: vertical scale exaggeratedControl joints: 4 panels, 6' × 6'2×4 forms, 16 stakes6 × 6 in wire meshGravel base, 6 in past every edge½ in joint at the house
Shopping list
BoughtItemBuyCost
Gravel base (crusher run)2.31 cu yd for 4 in compacted, 6 in past the open edges3.46 tons$155.73
Form boards (2×4)38 ft for three sides; the house wall is the fourth1 × 14 ft, 2 × 12 ft$22.80
Wood stakes (18–24 in)One every 3 ft and at each board end, plus 2½–3 in screws16$12.00
Expansion joint strip (½ in fiber)Isolation joint along 12 ft of house wall2 × 10 ft$16.00
Wire mesh (6 × 6 in, 5 × 10 ft sheets)132 sq ft, sheets lapped 6 in; tie the laps4 sheets$56.00
Rebar chairs (2 in)One every 3 ft each way, holding the steel at mid-depth25$6.25
Ready-mix concrete, delivered1.96 cu yd with 10% extra, rounded up to ¼ yd; incl. $100.00 fees2 cu yd$440.00
Cure & seal compound200 sq ft per gallon as a curing coat1 gallon$30.00
Estimated materials total$738.78
Excludes tax, tool rental, a pump if the truck can’t reach, and screws and tie wire. Unopened bags can usually be returned; running short mid-pour can’t be fixed.
Concrete needed1.96 cu yd52.8 cu ft · 1.5 m³4 in thick, plus 10% for spillage and an uneven base.
Cheaper: bags or ready-mixReady-mixSaves $132.00. 88 × 80 lb bags: $572.00 (7,040 lb to mix). 2 cu yd of ready-mix: $440.00 with fees.
Control joints4 panels, 6' × 6'24 ft of joints, cut or tooled 1 in deep (¼ of the slab).
Dig depth for a surface level with the ground8 in20.32 cm4 in slab + 4 in gravel, 6 in wider than the slab on the open sides.
Slope away from the house3 in7.62 cm¼ in per foot across the 12 ft side, so water runs off.
Soil to dig out and haul away5.02 cu yd3.83 m³4.01 cu yd in the ground grows about 25% once dug.
Slab area144 sq ft13.38 m²
Materials cost per sq ft$5.13

Order of work

  1. Call 811 (in the US) a few days before digging so buried utilities are marked, and ask your town whether the slab needs a permit — many limit paved area or set distances from property lines.
  2. Lay out the slab with stakes and string 6 in outside every edge, and set the strings at the finished height with a slope of ¼ in per foot away from the house.
  3. Dig to the depth shown above, measured down from the strings, and compact the soil. Spread and compact the gravel base in 2–3 in layers until a boot heel barely marks it.
  4. Set the forms on edge with their tops on the string line, stake them every 3 ft and screw through the stakes; cut stakes off below the top of the form so the screed board can pass. A 2×4 is only 3½ in deep, so under a 4 in slab pack gravel against the bottom of the board on the outside. Against the house, fasten the expansion joint strip to the wall instead.
  5. Place the mesh or rebar on chairs at mid-depth, 3 in in from the forms. Lap mesh sheets one full square and tie laps and rebar crossings with wire.
  6. Pour: have helpers, wheelbarrows and tools ready before the truck arrives or the first bag is mixed. Dampen the base, fill the forms to slightly above the top, and screed with a straight 2×4 in a sawing motion along the forms.
  7. Finish: bull-float right after screeding, wait until the surface water has gone, then round the edges with an edger, groove the control joints ¼ of the slab deep (or saw-cut them within 6–18 hours), and give it a broom finish for grip.
  8. Cure: spray or roll on cure & seal as soon as the surface can’t be marked, or keep the slab wet under plastic for 7 days. Strip the forms after a day or two, backfill the edges, and keep heavy loads off for a week.

Tools you’ll need

  • Plate compactor for the base (rental), shovels, a steel rake and wheelbarrows
  • Mixer (rental) if you use bags; a concrete rake or come-along to spread
  • Straight 2×4 screed board, bull float or magnesium float, edger and groover (or a saw for the joints)
  • Stakes, mason’s line, line level and a 4 ft level; drill/driver, circular saw and a sledgehammer for the forms
  • Bolt cutters for mesh or rebar, pliers and tie wire
  • Stiff broom, garden sprayer or roller for cure & seal
  • Waterproof gloves, rubber boots and safety glasses — wet concrete is caustic and burns skin

Tips before you buy

  • Get a ready-mix quote before buying bags. Above about a cubic yard the truck is usually cheaper, and it saves mixing 45 bags per yard by hand.
  • Ask the supplier how far the truck’s chute reaches and check it can park that close without crossing a lawn, septic tank or soft ground. If it can’t, budget for a pump or plenty of wheelbarrows and helpers.
  • Pour on a mild, overcast day if you can. Hot sun and wind dry the surface before you can finish it; don’t pour on frozen ground.
  • Oil or spray the inside of the forms with form release so they come off clean.
  • Driveways, garage floors, footings and slabs that carry a building need the thickness and reinforcement your local code or an engineer specifies; this planner lists materials, it doesn’t design structure.